Analysis and Evaluation of (β) Beta Distribution or Three Point Estimation for PERT Technique in Project Management
Ahraz Javeed Reshi
Abstract: Schedule Management is one of the key aspects of project management in view to ensure how effectively and efficiently the work gets delivered. There are various software?s which are primarily used for the planning and scheduling of the activities with respect to various methodologies used. One of the widely used defined as Three Point Estimation and beta Distribution model. Three Points is a technique used by professionals in estimating. This technique use the three figures that are produced initially for every distribution that is required, based on prior experience or best-guesses. The first is a most likely (M)/best guess (BG) which is the average amount of work the task might take if the team member performed it 100 times. The second estimate is the pessimistic (P) estimate which is the amount of work the task might take if the negative factors they identified do occur. The third estimate is the optimistic (O) estimate which is the amount of work the task might take if the positive risks they identified do occur. You may use the beta distribution method to calculate the three point estimating. As the most likely scenario has a more significant impact on the outcome, you multiply the value by 4 while the overall divisor increases to 6 which is further versed in the paper.
Keywords: Three Point Estimating, Beta Distribution, Factors, Schedule Management
Edition: Volume 12 Issue 9, September 2023
Pages: 1736 - 1738
DOI: https://www.doi.org/10.21275/SR23922120800
Make Sure to Disable the Pop-Up Blocker of Web Browser
Similar Articles
Downloads: 1
Review Papers, Construction Management, India, Volume 11 Issue 1, January 2022
Pages: 778 - 784A Review Paper on Prediction of Construction Productivity Using Artificial Neural Network Model
Kavya S. M., Nikhil T R, Akshayakumar V Hanagodimath
Downloads: 2 | Weekly Hits: ⮙1 | Monthly Hits: ⮙1
Student Project, Construction Management, India, Volume 10 Issue 6, June 2021
Pages: 1389 - 1395Contracting Strategies in Mid-Rise Buildings and Analysis Using SPSS Software
Hinsha P Nazer, Anju K
Downloads: 2
Student Project, Construction Management, India, Volume 10 Issue 6, June 2021
Pages: 1673 - 1676Quantitative Assessment of Impact Factors for Palarivattom, Kundanoor and Vyttila Flyovers
Rowbina, Mancy Kabeer
Downloads: 2 | Weekly Hits: ⮙1 | Monthly Hits: ⮙1
Research Paper, Construction Management, India, Volume 10 Issue 11, November 2021
Pages: 1163 - 1167Construction Industry Tomorrow: Post COVID - Implementations on Project Management Factors and Strategies
AR. Shilpa Muralidhar, AR. Salil Dogra, AR. Garima Singh
Downloads: 3 | Weekly Hits: ⮙1 | Monthly Hits: ⮙2
Research Paper, Construction Management, United States of America, Volume 13 Issue 10, October 2024
Pages: 1606 - 1610Material Cost Fluctuations: Analyzing the Effects of Market Volatility on Civil Project Budgets
Abhiram Reddy Anireddy